REG 418 - Gunnersbury Regeneration Project - Updates and Approvals

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Resolved:

 

That Cabinet agreed the recommendations of the report as follows:

 

1.     Cabinet noted and approved alternate funding of £560,757 from revenue in order to make up the shortfall of previously approved capital funding for the Heritage Lottery Phase of the Gunnersbury Project.

2.     Cabinet noted and approved a revenue contribution to capital of £500,000 to match the Gunnersbury element of a borough –wide ParkLife funding offer (Sports Phase).

3.     Cabinet authorised allocation of £96,984 of s106 Brentford schemes to the Gunnersbury Regeneration Project to meet the October 2014 Cabinet report contribution target.

4.     Cabinet gave approval for the procurement of an operator for the leisure facilities in the Sports Hub on a 10 year agreement, with an additional 5 year extension option. It is likely that this agreement will bring in additional capital funding required to complete the Sports Hub Phase of this project.

Publication date: 17/11/2016

Date of decision: 15/11/2016

Decided at meeting: 15/11/2016 - Cabinet